41. To reduce the cost of the electricity generated
- the load factor and diversity factor should be low.
- the load factor and diversity factor should be high.
- the load factor should be low but the diversity factor should be high.
- the load factor should be high but the diversity factor should be low.
42. What does the area under the load curve give
- load
- average demand
- energy consumed
- maximum demand
43. The ratio of energy produced in a given time to the maximum possible energy that can be produced is
- utilisation factor
- plant use factor
- demand factor
- load factor
44. Which of the following expressions depicts the utilization factor?
- ratio of maximum generator demand to the generator capacity
- ratio of actual energy produced to the generator capacity
- ratio of generator capacity to the maximum demand
- ratio of generator capacity to the actual energy produced
45. The load factor of the domestic load is
- 10 to 15 %
- 30 to 40 %
- 50 to 60 %
- 60 to 70 %
46. The area under daily load curve divided by 24 hours give
- average load
- least load
- peak demand
- total kWh generated
47. Load shedding is done to
- improve power factor
- run the equipment efficiently
- repair the machine
- reduce peak demand
48. A large diversity factor means
- increases the maximum demand
- increase the unit price of electricity
- reduces the unit price of electricity
- large plant capacity required
49. The yearly load duration curve of a power plant is a straight line. The average annual load is 400 MW. The capacity of the plant is 900 MW. The plant capacity factor will be
- 0.6
- 0.5
- 0.3
- 0.4
50. In a system, if the base load is the same as the maximum demand, the load factor will be
- 1
- 0.5
- 0
- infinity